Equipment List

To install the IR Thermography System, you need the equipment listed below. Some items are provided by Cutsforth, and some are provided by the electrical contractor.

Equipment

Supplied by Cutsforth

Supplied by Electrical Contractor

Infrared camera

checkmark.png

Controller (cRIO-9055 4-slot controller)

checkmark.png

NEMA 4X rated enclosures (camera enclosure, cRIO enclosure)

checkmark.png

Conduit

checkmark.png

Ethernet cable for data run from camera to cRIO

checkmark.png

Ethernet cable for connection to server

checkmark.png

600-volt-rated power cable

checkmark.png

Installation Overview

This section provides step by step instructions for installing the IR Thermography System.

  1. Mount the IR cRIO enclosure at the planned location.

  2. Mount the IR camera enclosure(s) at the planned location(s).

  3. Install the conduit and run cable between the IR cRIO enclosure and the camera enclosure(s).

  4. Install the conduits and run cables for AC power inputs to the cRIO enclosure and camera enclosure(s). Minimum circuit size: 20A circuit free of non-linear loads. Consider a circuit with isolated ground.

  5. Install the conduit and run cable for data connection to the cRIO enclosure. Cutsforth recommends Cat6a or fiber connection (media converter required if using fiber).

  6. Connect protective earth conductor per local electrical codes.

  7. Install wire for 120 to 240 VAC supply per local electrical codes.

  8. If required by local electrical codes, install an external switch or circuit breaker near the equipment. Ensure equipment is positioned so that it will not be difficult to operate the external disconnecting device.

Up to seven cameras can be connected to each cRIO, provided that cable lengths stay within the specified limitations.

Mounting and Placement Requirements

  • Cameras should be installed in a location with a direct line of sight to the equipment being measured.

  • The cRIO enclosure should be mounted in a location that accommodates the desired camera installation locations without exceeding the specified maximum cable run lengths.

  • Avoid mounting the cRIO enclosure in an area that experiences excessive direct sunlight, to avoid overheating.

  • The camera enclosure ships with both wall and pole mounting hardware options.

Note

Mount the camera so its line of sight is not obstructed by any material that is not IR-transparent. Materials such as glass, water, and most plastics pass visible light but block or distort infrared energy, and will produce inaccurate temperature readings even though they appear transparent to the eye.

Conduit and Strut Channel Recommendations

Component

Standard Recommendation

Recommendation for High-Corrosion Environments

Conduit type

Galvanized rigid metal conduit (RMC)

Rigid Aluminum Conduit (RAC)

Conduit fittings type

Malleable, NEMA 4X rated or greater

Aluminum

Strut channel type

Hot dipped galvanized, back-to-back

316 Stainless steel

Mounting hardware

316 Stainless steel

316 Stainless steel

Liquid flexible metallic conduit

Type HCX

Type HCX

Recommended Strut Rack Design for cRIO Enclosure

RecommendedStrutRack2078.png

A in. (mm)

B in. (mm)

C in. (mm)

68 (1730)

24 (610)

Refer to enclosure mounting feet dimensions

Cabling Requirements

The following table describes the conduit runs required between the plant power source, the camera enclosure(s), the cRIO enclosure, and the InsightCM Server.

Conduit Run

Conduit Trade Size

Wire Description

Purpose

Max Cable Length

Plant power to IR Camera Enclosure(s)

3/4 in (2 cm)

120 VAC power (20A dedicated circuit, preferably with isolated ground)

Power for the camera enclosure

N/A

IR Camera Enclosure to cRIO Enclosure

3/4 in (2 cm)

Cat6a

Data from camera to cRIO

100 ft

IR cRIO Enclosure to InsightCM Server

3/4 in (2 cm)

Cat6a or Fiber

Data to InsightCM Server

330 ft (100 m)

Plant power to IR cRIO Enclosure

3/4 in (2 cm)

120 VAC power (20A dedicated circuit, preferably with isolated ground)

Power for the cRIO enclosure

N/A

Note

cRIO enclosures do not come with conduit holes pre-drilled. Conduit sizing and hole placement is customizable. All conduit runs listed above are the responsibility of the plant electrical contractor.

Running Plant Power and Data Connections

The Ethernet cables from the camera(s) should be plugged into the Ethernet switch inside the cRIO enclosure. The Ethernet cable from the InsightCM server should be plugged into Port 0 on the cRIO.

Connect protective earth conductor per local electrical codes, and confirm the AC power circuit supplying each enclosure is sized per the Installation Overview before energizing the system.

Was this article helpful?
0 out of 0 found this helpful