PM Need: Required
Advised download frequency: Quarterly or more frequently based on plant preference, frequency of recordings created by threshold settings, or when prompted by a Storage Low warning.
Action: For information of downloading and deleting files, see Downloading Data.
PM Need: Required
Frequency: Annually
Action: Using a compressed-air duster approved for electronics, blow all dust and debris off the electrical components inside the Premium Monitoring System.
To access Premium Monitoring System components:
-
Pause monitoring.
-
Exit the Premium Monitoring System Application.
-
Turn off the blue Power switch.
-
Remove the remote meter points panel to gain access to the AC breaker and turn it off.
-
Visually inspect and air clean the monitoring system components. Remove the remaining faceplate with monitor only if conditions present require it.
Calibration Need: Required
Frequency: Annually or as outage schedule allows.
Action: Using a hand-held voltmeter, confirm that the converter output is within ±10% of 24 V. Adjust as necessary using an insulated small flat-blade screwdriver.
To adjust the output voltage:
Turn the screw inside the hole labeled Vout ADJ.
Calibration Need: Required
Advised Frequency: Every three years or anytime it is observed through experience that the touch screen accuracy is not acceptable
Action:
-
Exit the Premium Monitoring System Application.
-
On the Windows Desktop, in the lower-right corner of the screen next to the system date and time, find the icon for the PenMount Monitor.
-
Right-click the PenMount Monitor icon and select Control Panel.
-
Highlight the PenMount 6000 USB icon and click Configure.
-
Click the desired calibration method (Standard or Advanced).
-
Follow the prompts to complete the calibration.
Calibration Need: Advised
Frequency: Annually or as outage schedule permits
Calibration Need: No manufacturer's calibration advised