If AC power is supplied and the internal breaker is activated, you can turn the Premium Monitoring System on and off using the blue Power switch:

  • To power on, turn the Power switch to the right.

  • To power off, turn the Power switch to the left.

power-switch.png

Power-Up Sequence

  1. At power-up, the Power switch lights up and AC power is delivered to the internal AC-to-DC power converter.

    The Premium Monitoring System displays the Windows Desktop (WES7).

  2. After a short delay, the monitoring application starts automatically.

    NOTE:

    Do not interrupt the boot process unless specifically instructed to do so by Cutsforth support. The power-up sequence can take some time due to the fact that multiple devices are receiving power in a specific sequence.

  3. When the monitoring system application has successfully initialized, it displays the HOME page.

Power-Up Troubleshooting

  1. If the Power switch does not come on, confirm that the plant's 120 V AC supply circuit is on before opening the unit to inspect the internal breaker.

  2. Allow a few minutes for the Premium Monitoring System Monitoring Application to boot upon system startup. If the monitoring system does not automatically display the monitoring application within a few minutes of power-up, double-click the Premium Monitoring Application icon on the desktop: