Major Installation Steps

  • Mount the Wired Vibration Monitoring system enclosure at the planned location.

  • If not already installed, install vibration sensors at the desired locations on equipment to be monitored.

  • Install conduit and run shielded signal cabling between the vibration sensors and the monitoring system enclosure. Maximum cable length is dependent on the sensor, frequency range of interest, and power supplied by the input card.

  • Install conduit and run cable for AC power input to the monitoring system enclosure. Minimum circuit: 20 A, 120/240 VAC, free of non-linear loads. A circuit with an isolated ground is recommended.

  • Install conduit and run cable for the data connection. Cutsforth recommends Cat6a or fiber (fiber requires a media converter). Refer to cable specifications for recommended maximum cable lengths.

  • Ensure the plant’s InsightCM server is set up and ready to communicate with field equipment prior to Cutsforth commissioning.

Conduit Layout Summary

Color

Conduit Run

Trade Size

Wire Type

Max. Length

Supplied By

Blue

Monitoring Enclosure to InsightCM Server

¾ in. (2 cm)

Cat6a or Fiber

Refer to cable specifications

Plant Electrical Contractor

Red

Plant Power to Monitoring Enclosure

¾ in. (2 cm)

120/240 VAC, 20A dedicated circuit (isolated ground preferred)

N/A

Plant Electrical Contractor

Yellow

Vibration Sensor(s) to input modules in the Enclosure

¾ in. (2 cm)

Shielded signal cabling

Depends on sensor, frequency of interest, and input module

Plant Electrical Contractor