The following tables summarize the responsibilities of Cutsforth and the Plant during the four project phases:

Planning Phase

Task

Cutsforth

Plant

Review this planning guide document and share it with key plant personnel involved in the project.

checkmark.png

Determine enclosure mounting positions and conduit routes customized to the generator and ensure that they are within system guidelines.

checkmark.png

Select an Electrical Contractor and Coordinate.

checkmark.png

Preparation for Service Phase

Task

Cutsforth

Plant

Determine the HFCT installation location(s) with help from Cutsforth, using the Planning the Current Transformer (CT) Locations section of this document for guidance.

checkmark.png

checkmark.png

Determine the monitoring system enclosure mounting location and conduit routing and ensure it is within system requirements.

checkmark.png

Mount the monitoring system enclosure with supporting strut channel rails and install required conduit.

checkmark.png

Cutsforth Service Phase – Cutsforth Technicians On-site

Task

Cutsforth

Plant

Ensure the generator is in the needed condition for the scope of work.

checkmark.png

LOTO requirements: Depends upon installation approach.  It is possible to perform this installation with the generator in service.

checkmark.png

Provide 120V power (GFI-protected is preferred) for installation tooling.

checkmark.png

Provide adequate working access to the installation site including scaffolding if required for worker access.

checkmark.png

Perform system testing and commissioning.

checkmark.png

Provide control room support for testing signal outputs.

checkmark.png

checkmark.png

InsightCM Phase

Task

Cutsforth

Plant

Review InsightCMTM Server Requirements.

checkmark.png

Procure a server for InsightCMTM (if not done already).

checkmark.png

Verify that server meets requirements before installing software.

checkmark.png

Verify server prerequisites are checked (IIS Role).

checkmark.png

Install InsightCMTM on the server.

checkmark.png

Install the Google Chrome browser on the server.

checkmark.png

If using a Windows 10 server, inquire with Cutsforth about the NI RAD Utility. Otherwise, skip this step.

checkmark.png

Power on the Cutsforth monitoring equipment.

checkmark.png

Configure IP addresses for the Cutsforth monitoring equipment from the server.

checkmark.png

Connect the Cutsforth device to the server using an Ethernet or fiber cable.

checkmark.png

Create the device’s asset tree in InsightCMTM and validate.

checkmark.png

Create the device in InsightCMTM using the configured IP addresses.

checkmark.png

Configure desired alarm settings, if desired alarms are known.

checkmark.png

Using InsightCMTM, establish a connection to the field device.

checkmark.png

Confirm data is being collected, can be viewed in InsightCMTM, and is accurate. This task would likely be performed by Cutsforth’s Software and Electronics team after the service portion of the installation has been completed.

checkmark.png

checkmark.png

Cutsforth offers all of the tasks listed in the InsightCMTM Phase as a service. Please inquire if you are interested in having Cutsforth perform these tasks.

Was this article helpful?
0 out of 0 found this helpful