Related Products: |
EGMA-004, EGMA-005, EGMA-006, EGMA-007, EGMA-008, EGMA-013, EGMA-015, EGSA-013, EGSA-015, EGSA-210, EGSA-220 |
Related Documents: |
EZDP-2040 |
Type: |
Installation |
Keywords/Labels: |
responsibilities, who does what |
Summary: |
Describes who is responsible for each installation task: Cutsforth or installer |
Responsibilities |
Cutsforth |
Plant |
---|---|---|
Provide shaft growth value at grounding location |
![]() |
|
Indicate shaft rotation direction |
![]() |
|
Review planning guide document |
![]() |
|
Determine enclosure mounting position and conduit routes customized to the generator and ensure it is within system guidelines |
![]() |
|
Mount enclosure(s) and install required conduit |
![]() |
|
Ensure the shaft is off turn gear and stationary |
![]() |
|
Ensure the shaft is fully coupled |
![]() |
|
Ensure the bearing caps immediately adjacent to the shaft grounding area are in place |
![]() |
|
LOTO requirements: Main excitation system, ground detection system, and turning gear |
![]() |
|
Provide 120V GFI protected power |
![]() |
|
Provide adequate working access to installation site including scaffolding |
![]() |
|
Install Cutsforth shaft assembly |
![]() |
|
Provide welding support |
![]() |
|
Run wiring in completed conduit raceways |
![]() |
|
System wiring terminations not including grounding termination to generator case |
![]() |
|
Identify main grounding termination point on the unit case |
![]() |
|
Electrical support to make ground terminations |
![]() |
|
System testing and commissioning |
![]() |
|
Control room support for testing 4-20mA outputs if connecting to DCS |
![]() |