Summary: |
Describes who is responsible for each installation task: Cutsforth or installer |
Responsibilities |
Cutsforth |
Plant |
---|---|---|
Provide shaft growth value at grounding location |
||
Indicate shaft rotation direction |
||
Review planning guide document |
||
Determine enclosure mounting position and conduit routes customized to the generator and ensure it is within system guidelines |
||
Mount enclosure(s) and install required conduit |
||
Ensure the shaft is off turn gear and stationary |
||
Ensure the shaft is fully coupled |
||
Ensure the bearing caps immediately adjacent to the shaft grounding area are in place |
||
LOTO requirements: Main excitation system, ground detection system, and turning gear |
||
Provide 120V GFI protected power |
||
Provide adequate working access to installation site including scaffolding |
||
Install Cutsforth shaft assembly |
||
Provide welding support |
||
Run wiring in completed conduit raceways |
||
System wiring terminations not including grounding termination to generator case |
||
Identify main grounding termination point on the unit case |
||
Electrical support to make ground terminations |
||
System testing and commissioning |
||
Control room support for testing 4-20mA outputs if connecting to DCS |