Summary:

Describes who is responsible for each installation task: Cutsforth or installer

Installation Responsibilities

Responsibilities

Cutsforth

Plant

Provide shaft growth value at grounding location

checkmark.png

Indicate shaft rotation direction

checkmark.png

Review planning guide document

checkmark.png

Determine enclosure mounting position and conduit routes customized to the generator and ensure it is within system guidelines

checkmark.png

Mount enclosure(s) and install required conduit

checkmark.png

Ensure the shaft is off turn gear and stationary

checkmark.png

Ensure the shaft is fully coupled

checkmark.png

Ensure the bearing caps immediately adjacent to the shaft grounding area are in place

checkmark.png

LOTO requirements: Main excitation system, ground detection system, and turning gear

checkmark.png

Provide 120V GFI protected power

checkmark.png

Provide adequate working access to installation site including scaffolding

checkmark.png

Install Cutsforth shaft assembly

checkmark.png

Provide welding support

checkmark.png

Run wiring in completed conduit raceways

checkmark.png

System wiring terminations not including grounding termination to generator case

checkmark.png

Identify main grounding termination point on the unit case

checkmark.png

Electrical support to make ground terminations

checkmark.png

System testing and commissioning

checkmark.png

Control room support for testing 4-20mA outputs if connecting to DCS

checkmark.png