Perform this procedure to confirm the proper wiring of the junction box and Remote Meter Point or Assurance Monitoring System.
Remove ropes from the Shaft Grounding Assembly. See the Removing a Rope section in Replacing a Rope Refresh Kit | Series 2.
Check that continuity exists between the Remote Meter Point or Assurance Monitoring System panel ground points and turbine ground.
Check that continuity exists between the Remote Meter Point or Assurance Monitoring System panel shaft voltage test point and the metering rope.
Install ropes into the Shaft Grounding Assembly. See the Inserting a Rope section in Replacing a Rope Refresh Kit | Series 2.
Measure the resistance between the shaft and the case to which the ground connection is made and confirm it is less than 1 ohm.