Related Products: |
EGSA-210, EGSK-201, EGSK-301 |
Related Documents: |
EZDP-2035 |
Type: |
Installation |
Keywords/Labels: |
Shaft Grounding, Installation |
Summary: |
Instructions for making sure rope contact points are touching the rope guide spaces and tightened. |
-
Adjust each rope guide section so that the contact points (A) are touching the 1/16 in rope guide spacer.
-
Tighten all the 5/16 in-18 x 5/8 in bolts (B) on the rope guide starting closest to the attachment arm side of the assembly, and then work around from there. Torque all the bolts to 220 in lbs.
-
When all rope guide bolts are torqued and the rope guide is secured, remove the rope guide spacer.
Submit your questions or requests using the Support Ticket Submission form.