Summary: |
Generator conditions that must be established for a successful installation. |
-
The shaft must be fully coupled.
-
The generator and turbine bearing caps in the load compartment must be fully installed.
-
The condition of the shaft at the Shaft Grounding Assembly installation location must be documented by photo or video. If the shaft is still rotating, use a strobe to capture a video of the shaft condition. To facilitate a robust electrical contact for the shaft grounding system, make sure that the shaft surface is free of grooving, pitting, oxidation, and contamination.