Required Tools

  • Welder, TIG preferred (for Shaft Grounding Assembly only)

  • 1/2 in hex wrench socket

  • 9/16 in socket wrench

  • 1/4 in hex key wrench

  • 3/16 in hex key wrench

  • Drill

  • 5/16 in-18 tap

  • Letter F drill bit

  • Wire cutters

  • Wire strippers

  • Wire crimpers

  • Tape, banding, and/or clamps (for Shaft Grounding Assembly only)