Related Products:

EGSK-301, EGMA-301, EGSK-201, EGMA 203

Related Documents:

EZDP-2041, EZDP-2046

Type:

Installation

Keywords/Labels:

Assurance Monitoring, Remote Meter Point, Installation

Summary:

Information on alternate ground wire locations.

Additional Ground Wire Routing Information

The turbine case is the preferred grounding location. The ground conductor should run the shortest route possible, up to a maximum of 47 ft. 

NOTE

Do not run the ground wire an excessive distance in an attempt to terminate to an existing grounding pad. A short run is the best run.

Grounding to the generator case is an alternate option that should be used if it facilitates a shorter overall ground run. However, it typically results in a much noisier ground reference and may introduce unwanted interference, especially when measuring with a handheld oscilloscope.

gw-reroute-500px.png

circle-a.png Junction box

circle-b.png Remote Meter Point or Assurance Monitoring System