Summary:

Generator conditions that must be established for a successful installation.

Installation Prerequisites

  • The shaft must be fully coupled.

  • The generator and turbine bearing caps in the load compartment must be fully installed.

  • The condition of the shaft at the Shaft Grounding Assembly installation location must be documented by photo or video. If the shaft is still rotating, use a strobe to capture a video of the shaft condition. To facilitate a robust electrical contact for the shaft grounding system, make sure that the shaft surface is free of grooving, pitting, oxidation, and contamination.